Fabrication route comparison

Factory-Cut or Site-Cut FRP Grating: Compare the Finished Job

The lower “cutting” line is not automatically the lower installed cost. Compare both routes on the same finished pieces, edge treatment, acceptance, waste, labour, access, rework and schedule.

Prepared by Dengtai Industry
Published · Reviewed

Same duty and finished pieces Labour and waste included Edge and inspection explicit As-built risk visible
Workers finishing molded FRP grating panels in the factory

Controlled fabrication is one route to the finished job, not automatically the only correct route. Photo: Dengtai Industry.

Cost terms

What Factory-Cut and Site-Cut Costs Must Include

Define each route as the work needed to deliver the same accepted pieces.

Factory-cut route
Finished pieces are produced from an approved list in the works, with the agreed cutting, opening formation, edge treatment, inspection, marking and packing completed before dispatch.
Site-cut route
Full panels or oversized pieces arrive on site and are measured, cut, drilled, finished, sealed and inspected by the installation team or a local fabricator.
Finished-job cost
The complete cost of producing, delivering and accepting the same installed pieces. It includes more than the panel price or the visible cutting fee.
Engineering basis
The load class, clear span, support layout, bearing contact, opening support and fixing condition that remain common to both fabrication routes.
Labour and access
The people, supervision, tools, working area, dust controls, lifting and downtime required to complete the cut. A slow or remote site can make the same operation materially different.
Yield and offcut
How much source panel is used and what remains after nesting or field cutting. Finished-piece area does not show the full source material consumed.
Rework
Additional labour and material needed when a piece is measured, cut, sealed or installed incorrectly. The comparison should estimate the route’s exposure to rework instead of assuming zero.

When to compare

When the Cutting Location Changes the Finished-Job Risk

Stable production and as-built adjustment create different cost and control profiles.

Specify this if…

  • Freeze the engineering duty before comparing routes; cutting location cannot replace the load, support and bearing review.
  • Choose factory cutting when dimensions are stable, the layout is repeatable and controlled cutting/sealing before dispatch reduces site work.
  • Choose site cutting when final dimensions must follow an as-built structure, the work is a small adjustment, or transport and handling make full-panel supply impractical.
  • Compare the routes when the site has limited cutting space, dust controls or sealing facilities.
  • Compare the routes when shutdown time, installation labour or rework has a major project cost.
  • Keep both routes available when most pieces are known but a few openings require field measurement.

Look elsewhere if…

  • One offer compares full panels with another supplier’s finished pieces using different resin, surface, mesh or panel format.
  • The factory route assumes that the drawing is correct and the site route assumes that field measurement has no schedule cost.
  • Edge sealing, first-piece checks, labels and packing are present in one route and excluded from the other.
  • A “cutting fee” is the only site-cut cost counted. Labour, tools, PPE, waste and rework are omitted.
  • The project has not decided whether the delivered responsibility is a full panel or an accepted finished piece.

Route compare

Factory-Cut and Site-Cut FRP Grating Compared

Match the finished job first, then compare where the work, risk and evidence sit.

Swipe horizontally to view all columns.

Finished-job inputFactory-cut routeSite-cut route
Engineering duty Same load class, support layout, bearing contact, opening support and fixing review; fabrication location does not waive them Same load class, support layout, bearing contact, opening support and fixing review; field measurement does not waive them
Dimensional basis Approved piece list, drawing revision and factory first-piece check As-built measurement by the site team, with changes controlled against the drawing
Cutting labour Included in the fabrication price or stated as an exclusion Site labour, supervision and downtime must be counted
Tools and consumables Controlled workshop equipment and blades Saw, blades or discs, drill bits, clamps, guide, extraction and spare consumables
Dust and site controls Extraction and workshop controls within the agreed fabrication scope Barriers, ventilation, PPE, cleaning and waste handling at the actual site
Yield and waste Nesting loss and source-panel use can be stated Offcuts remain on site and may require extra source panels
Edge treatment Named faces can be sealed, cured and inspected before packing Site must provide compatible sealer, clean conditions, cure time and inspection
Identity and packing Piece marks, requested packets, labels and packing list can be coordinated Site must maintain piece identity after full panels are opened or cut
Change and rework Pre-production changes are reviewed before cutting; late changes may alter material and schedule Field changes are easier to attempt but can create edge, fit, sealing or rework problems

Cost map

Four Cost Layers Missing From a Basic Cutting Price

The panel and visible cutting line are only the start.

Start with the same finished pieces

Both routes must match engineering duty, product row, marks, dimensions, openings, orientation, edge treatment, tolerance and delivery point.

Include the hidden site cost

Site cutting carries labour, supervision, tools, PPE, extraction, waste, cleaning, sealing and possible rework even when the saw is already owned.

Include the hidden factory coordination

Factory cutting requires an approved piece list earlier, material nesting and potentially longer pre-production coordination.

Price risk, not only material

An as-built retrofit can justify field adjustment; a repeat production order usually gains more from controlled factory fabrication.

We quote factory cutting from the agreed production scope. Site cutting remains appropriate for measured changes, repairs and as-built conditions, but its full labour and control scope belongs beside the factory price.

Work conditions

What Changes the Factory-versus-Site Decision

Repetition, shape, access, direction and as-built uncertainty all move the balance.

Swipe horizontally to view all columns.

Work conditionFactory-cut considerationSite-cut consideration
Repetitive long straight pieces Fixture setup and nesting can improve consistency Repeated measuring and handling consume site labour
Curves, notches and small openings Controlled tooling and first-piece approval reduce repeated interpretation More handling, blade changes and rework risk
Pultruded bearing bars Direction can be marked through fabrication and packing Site rotation or mixed panels can be difficult to detect
Remote or congested site Finished pieces may reduce shutdown and dust work Tool, power, access and waste facilities may be limited
As-built retrofit A wrong frozen dimension may stop or delay the order Measuring in place can justify a controlled field cut
Corrosive or immersed service Factory edge preparation, sealing and inspection can be linked Field sealing depends on weather, cleanliness and cure control

Comparison method

Compare Factory and Site Cutting in Five Steps

Normalize the finished pieces before adding route-specific cost and risk.

01
Start with one finished-piece schedule

Define engineering duty, product configuration, marks, dimensions, direction, openings, tolerances and edge treatment for both routes.

02
List every cost layer

Add panel, fabrication, labour, consumables, controls, waste, sealing, inspection, packing, freight and rework exposure.

03
Review access and schedule

Account for lifting, workspace, shutdown, supervision, dust barriers and the time the site can give the work.

04
Compare the accepted condition

Confirm that both routes deliver pieces accepted against the same drawing revision and inspection criteria.

05
Choose the route and record exclusions

Freeze whether the factory or site owns measuring, cutting, edge treatment, identification and correction.

The Comparison Begins With One Finished Job

Factory cutting and site cutting are not competing products. They are two ways to produce the same installed pieces. The comparison is valid only when both routes use the same grating row, mesh, resin, surface, piece marks, finished sizes, openings, direction and edge treatment.

That sounds obvious, but quotations often compare different scopes. One price may be a full panel delivered to site; another may be finished, sealed, marked pieces packed for installation. The second includes work that the first has not priced. Comparing the headline totals directly can make either route look cheaper for the wrong reason.

Start with the accepted finished piece. The supporting resource Ordering Cut-to-Size FRP Grating from a Piece List defines the drawing, datum, marks, openings and edge scope. This comparison uses that common object to decide where fabrication should happen and what every route costs.

Freeze the engineering duty before the route

The fabrication route does not decide the required load class, clear span, support positions, bearing contact or opening support. Those conditions belong to the installed design and stay common to both quotes. If one route assumes a different frame, a reduced bearing edge or an unreviewed opening, the comparison has changed the engineering duty rather than found a cheaper way to complete the same job.

Record the design basis before adding route-specific prices. At minimum, identify the load or duty the grating serves, the support and span arrangement, the expected contact at each bearing edge, the fixing scheme and any framing around cut openings. A measured retrofit can transfer measurement responsibility to the site, but it does not transfer away the need for that review.

FRP grating factory-cut and site-cut routes compared by finished scope, labor, waste, sealing and delivery
The route with the lower cutting line can still carry a higher finished-job cost when labour, waste and rework remain with the site.

What Factory Cutting Moves Into the Quotation

Factory cutting moves layout interpretation, nesting, cutting, drilling, edge treatment and piece identification into a planned production route. Those operations can happen before the panels are packed and can be checked against the agreed list.

The commercial benefit is not that factory labour is automatically lower. It is that the work becomes visible in one fabrication scope. The buyer can see which pieces are produced, how much source panel is consumed and whether sealing, first-piece checks, labels and packing are included.

There is also a coordination cost. The piece list must be frozen earlier. A late dimension change may alter nesting, material use and production sequence. If the structure is still being measured or the layout is likely to change, an early factory-cut order can lock in the wrong information.

Factory cutting cannot correct the drawing

The factory can identify missing fields and stop the release, but it cannot know that a pipe has moved or a support was never installed unless the project reports it. Precise cutting makes a wrong approved dimension more certain, not more correct. Responsibility for the as-built information must remain visible.

What Site Cutting Leaves With the Installer

Site cutting leaves final measurement and fabrication close to the structure. That can be valuable for a retrofit where the opening, frame or support position has changed. The installer can respond to the actual fit and avoid waiting for a new factory piece when only a small trim is needed.

The cost is broader than a saw and an operator. Site cutting includes measuring, marking, supports, guides, blades, drilling, PPE, dust barriers, extraction or ventilation, waste handling, edge preparation, sealing, cure protection, inspection and correction. On a remote or congested site, it may also include extra access, supervision, temporary protection and lost production time.

The site-cut quote needs to say whether the contractor owns all of those steps. A “labour included” line does not explain whether sealing and first-piece inspection are included, or whether failed pieces are rework at the contractor’s cost.

Count Yield, Offcuts and Extra Panels

The finished-piece area is not the whole material story. A factory nesting layout can show how full panels are consumed and may identify layouts that use offcut or require an extra source panel. A site-cut route can also use offcuts, but the usable yield depends on the actual sequence, tool access and whether workers preserve remaining material.

Ask both routes to compare the same finished pieces with a stated allowance for blades, edge trim and defective or unusable cut pieces. Avoid applying a universal waste percentage. Small pieces, curved shapes, small openings and mixed orientations can change the layout.

The full-panel versus cut-piece pricing guide shows why finished area and source-panel area answer different questions. This guide adds the site labour and routine-cut cost to that earlier commercial comparison.

Put Edge Sealing and Inspection in the Right Route

Factory fabrication can include cleaning, sealing, controlled cure and inspection before packing when those steps are ordered. The quotation should name which faces are sealed and what record is kept. A factory cut price that excludes edge treatment is not equivalent to a site route that includes it.

Site sealing can be appropriate when it uses a compatible product, a clean and dry surface, correct application, sufficient cure and inspection. The difficulty is environmental control: wind, dust, rain, high humidity, cold or early handling can interfere. For severe chemical, immersion or coastal duty, the sealer and application method should be approved for the actual exposure.

The cutting and edge-sealing guide explains that the seal protects the exposed face but does not restore bars, bearing or load capacity. Both fabrication routes still require the support and opening review.

Exposed cut edge and shaped opening in FRP grating
The edge-treatment route belongs beside the cutting route; sealing must be applied, cured and inspected rather than assumed. Photo: Dengtai Industry.

Compare Labour, Access and Schedule

Installation labour is the largest part of many site-cut comparisons, but the correct number is project-specific. Estimate the hours for measuring, setup, cutting, drilling, grinding, sealing, cleaning and inspection. Include the time to move full panels through the site and remove offcuts. Add supervision and the cost of stopping adjacent operations.

Factory cutting changes the schedule rather than eliminating duration. It adds drawing coordination and production lead time before shipment, but can reduce the work on the critical site path. The relevant comparison is the time to an accepted installed piece, not the time to a panel price.

For a shutdown or hazardous area, the schedule difference can dominate the material difference. The offshore platform guide is an example of a project in which access and controlled fabrication can outweigh a simple material comparison.

A Worked Comparison Skeleton Without Invented Prices

A reliable worksheet can use the project’s real quantities while leaving the monetary rates for the actual suppliers. Start with one row per finished piece mark and its quantity. Create the following columns:

Cost or conditionFactory-cut routeSite-cut route
Product and finished piecesSame product row, marks, sizes and orientationSame product row, marks, sizes and orientation
Source materialSource-panel area and nesting loss stated in the fabrication quoteFull-panel quantities plus expected usable offcut
Cutting and drillingCutting, opening, drilling and handling scope included or excludedEstimated labour hours plus supervision
Edge treatmentFaces, sealer, cure, inspection and marking statedSite PPE, cleaning, sealer, cure protection and inspection
ScheduleDrawing freeze, production lead time and dispatchSite access, setup, shutdown and sequence
Defects and reworkResponsibility and first-piece acceptance statedLabour and material exposure for rejected or misfitting pieces
Packing and deliveryPiece labels, protection, packing and freightReceiving full panels, storing offcuts and moving material

The route total is not the panel rate. It is the sum of the visible supply scope and the project-side work needed to reach the accepted installed piece. If a value is unknown, leave it visibly unknown rather than inserting an invented percentage or hourly rate.

Use sensitivity instead of confidence

If site access is uncertain, calculate the site-cut route under a short and a long access window. If the drawing may change, compare the cost and schedule of a factory revision against a controlled field adjustment. This shows which assumptions actually control the decision.

For example, a stable 20-piece solar strip schedule may favour factory cutting because repetition and packing identity can be controlled. A single trench cover measured against an uneven existing frame may favour a controlled site adjustment. The same comparison rule can lead to different answers because the work conditions differ.

A Responsible Route Decision

Factory cutting is usually the stronger starting point when the layout is stable, repeatable, shaped or direction-sensitive, and when edge sealing and piece identity should be controlled before dispatch. Site cutting is usually the stronger adjustment route when actual conditions must be measured, or when one small change can be completed with controlled field procedures.

A hybrid order can be valid. Produce the stable pieces at the factory and leave a defined measured piece or opening for site approval. Record which parts are covered by the factory list, which are site-fit items and which person releases the final cut.

Do not compare a fully controlled factory piece with an informal site trim and call both “cutting”. Make labour, waste, edge treatment, inspection, schedule and rework visible, then choose the route that leaves the least unresolved risk with the party best able to control it.

What Makes a Cutting Comparison Invalid

A comparison becomes misleading when the routes do not share the same product or accepted result. Different resin systems, grating depths, mesh, surface or panel formats are different products, even if the outlines look alike. A full-panel offer and a finished-piece offer also need their exclusions translated into the same delivered scope.

Another error is treating the site’s existing equipment as free. A saw and operator still consume working time, consumables, supervision and space. Extraction, PPE, cleaning and waste removal may be supplied by other contractors, but their cost remains in the project. A factory quote should likewise show whether cutting, sealing, first-piece inspection, labels and packing are included.

Finally, do not assume that either route removes the need for site verification. Factory cutting transfers an earlier dimensional decision, while site cutting transfers execution risk to the field. In both cases, someone must verify the actual structure, the delivered or finished piece and the accepted support condition.

The most defensible decision records these assumptions beside the chosen route: drawing revision, pieces, factory exclusions, site exclusions, edge-treatment responsibility, schedule basis and change owner. That record is more valuable than a bare “factory cheaper” or “site faster” conclusion.

Required inputs

What a Complete Cutting-Route Comparison Must Show

Every omitted cost or responsibility becomes an assumption in the cheaper route.

  • Engineering duty — Load class, clear span, support locations, bearing contact, opening support and the fixing review.
  • Finished-piece scope — Product row, piece marks, quantities, dimensions, openings, orientation and tolerances.
  • Factory scope — Nesting, cutting, drilling, edge sealing, first-piece check, labels, packing and freight included in the offer.
  • Site scope — Labour hours, supervision, tools, consumables, PPE, dust control, cleaning, waste and rework exposure.
  • Access and schedule — Lift, workspace, power, weather, shutdown, production lead time and installation sequence.
  • Edge and inspection — Who seals which faces, how cure is controlled, who accepts the cut and what record is retained.
  • Identity and delivery — Piece marks, labels, packing method, receiving check and the person who controls substitutions.

Applications

When Factory Cutting or Site Cutting Makes More Sense

The right answer follows the installation condition rather than a universal preference.

Repeat solar maintenance strips

Repeated short pieces usually benefit from a frozen piece list and factory checks; field measurement remains necessary for the actual rail conditions.

Retrofit around existing equipment

The final opening may need a measured site adjustment after the support and clearance are confirmed.

Pultruded walkway on existing beams

Factory direction marks help, but the site must still verify beam positions and both bearing-bar ends.

Remote site with limited cutting controls

Moving cutting to the factory can reduce site dust, tool demand and shutdown time when dimensions are reliable.

Last-minute trench-cover correction

A field trim may be the practical option when the frame differs, provided bearing, lifting and edge protection are rechecked.

Cut-to-size piece-list preparation

Before either route is priced, turn the drawing into a production-level list with controlled identity.

Factory view

Put the Cost Where the Work Happens

A real comparison includes both visible invoices and hidden site coordination.

Factory-cut FRP grating pieces with curved and notched openings
Finished geometry is visible here; the route comparison must also account for labour, sealing, waste, inspection and schedule.

Keep the finished scope constant

Product, pieces, openings, edges, tolerance and acceptance must be identical before either route is ranked.

Count labour and access

Site time, supervision, tools, dust controls, waste and shutdown are part of cutting, even when no invoice names them.

Put the risk where it belongs

Factory coordination risk and site rework risk both need an owner and a comparison assumption.

Review route

From Finished Layout to a Documented Cutting Decision

Both options start from one piece schedule and one acceptance condition.

01
Send the finished layout

Share the drawing, support information, openings and desired edge condition with any known as-built constraints.

02
Freeze the comparison inputs

The same piece marks, product configuration, tolerance and acceptance are used for both routes.

03
Quote factory fabrication

The factory scope lists cutting, drilling, sealing, inspection, marking, packing and freight included.

04
Add the site-cut budget

The project or contractor adds labour, supervision, tools, PPE, dust control, waste, sealing and rework.

05
Choose and document the route

The accepted method names who measures, cuts, seals, inspects, identifies and corrects each finished piece.

Request a comparison

Send the Finished Job and Site Constraints

We will separate factory scope from the site work needed for a valid route comparison.

  • Molded and pultruded grating produced in house
  • Full panels or factory cut-to-size pieces
  • No fixed minimum order quantity
+ More specifications (size, quantity, span, environment)

PDF, DWG/DXF, image or Office file. If the file is larger than about 10 MB, email it to sales@frpgratingco.com instead.

Molded and pultruded grating · Full panels or cut to size · No fixed minimum order

Factory-Cut and Site-Cut FRP Grating Questions

Is factory cutting always cheaper than site cutting?

No. The answer depends on the finished pieces, site labour, access, seals, waste and rework exposure. Factory fabrication adds earlier drawing coordination, while site cutting adds on-site labour and control.

When is site cutting the better route?

Site cutting can suit as-built changes, retrofits, repairs and small final adjustments. It remains a controlled task because the panel needs support, correct tooling, dust protection, edge treatment and inspection.

Does factory cutting remove all site measurement?

No. The receiving team should still verify the delivered pieces against the drawing and the actual structure. A changed frame does not become the factory’s responsibility merely because the pieces were precut.

Can the cheaper cutting route avoid a load or support review?

No. Factory and site cutting are fabrication routes, not structural approvals. Load class, support spacing, bearing contact, opening support and fixing adequacy must be confirmed before either route is compared.

Which route gives better sealed edges?

Factory fabrication can apply and inspect agreed edge treatment under controlled conditions. Site sealing can be effective when the right sealer, clean surface, cure conditions and inspection are available.

How do I compare the two quotations?

Put both on the same piece marks, product configuration, openings, edge treatment, tolerance, delivery point and acceptance condition. Then add the site costs missing from the factory offer or the fabrication costs missing from the site route.

This content was prepared and reviewed by Dengtai Industry’s technical and production team using the project conditions, available product data and applicable documents. Limits that require design, testing or approval are identified in the content. Content last checked: